Do rooftop photovoltaic panels actually increase fire risk?
Photovoltaic panels do not spontaneously ignite a fire simply by their presence, but they introduce an electrical risk source distinct from the rest of the building: the direct current (DC) circuit connecting the panels to the inverter remains energized whenever there is light, even when the main power supply is cut off. This specific point justifies a dedicated risk analysis, not a generalization such as "PV is dangerous".
This analysis falls under the responsibility of the prevention advisor, within the framework of general fire prevention obligations in the workplace provided by the Code on Well-being at Work (Book III, Title 3). It must cover the PV electrical installation like any technical installation at risk, in the same way as a boiler room or battery charging area.
What are the hot spots and electrical arcs involved?
Hot spots and electrical arcs mainly originate from connection faults in the DC circuit: poorly crimped or corroded connectors, cables damaged by UV or rodents, junction boxes that overheat, cells degraded by microcracks creating localized resistance zones.
A DC electrical arc differs from an alternating current arc by its difficulty to self-extinguish: without a zero-voltage crossing, the arc can persist and significantly raise the local temperature, enough to ignite insulating materials or the roof waterproofing membrane. Junction boxes and quick connectors (MC4 type) are the most frequently identified failure points in industry feedback, well before the cells themselves.
Do photovoltaic panels complicate firefighter intervention?
Yes, and this is the main issue from a fire safety perspective: panels remain energized in daylight even after the main circuit breaker is cut, exposing intervention teams to electrocution risk if they cut a cable or perforate a panel without precaution.
Emergency zones (hulpverleningszones) integrate this parameter into their intervention doctrine: attack from a safe distance, no direct water jet on panels at close range, vigilance regarding roof overload in case of snow or panels deformed by heat. The PV installation can also hinder natural roof ventilation or access for smoke venting, which must be anticipated during installation, in consultation with the competent emergency zone.
Should fire detection be adapted in the presence of PV panels?
Fire detection must be adapted at the level of technical rooms related to PV (inverter room, cable trays crossing the building), not necessarily on the panels themselves which are outdoors. The NBN S 21-100-1 standard governs the design of detection installations inside buildings; it therefore fully applies to the inverter room and technical ducts through which DC cables enter the building.
There is no standard in Belgium dedicated exclusively to fire detection of outdoor rooftop panel arrays. The basic principle remains that of the Royal Decree of 7 July 1994: any installation that modifies the fire load or building risks must be subject to an assessment integrated into the overall risk analysis, depending on the building classification (low, medium or high).
How to signal a PV installation to intervention teams?
Signage of a photovoltaic installation to firefighters involves a standardized pictogram indicating the presence of panels and the location of cut-off points, posted at the main entrance, technical room and roof access points. The objective is for an intervention team to know, before going up to the roof, that they are dealing with an electrical source that cannot be completely cut off at the main circuit breaker.
This signage must be consistent with the intervention file provided to the emergency zone: installation plan, location of DC panels, position of the rapid shutdown device if it exists. ANPI constitutes a useful resource to guide operators on signage best practices, in the absence of a single detailed prescription in current Belgian regulations.
What best practices to reduce fire risk related to photovoltaics?
Reducing fire risk related to photovoltaics relies first on preventive maintenance of the DC electrical installation, even before detection: periodic inspection of connectors, infrared thermography to identify hot spots before they become critical, verification of cable and junction box condition.
Best practices to integrate into building operation:
- have the panel array layout and roof clearance zones validated by the competent emergency zone;
- equip the inverter room with detection compliant with NBN S 21-100-1, like any other technical room at risk;
- document the presence of the DC rapid shutdown device in the file provided to firefighters;
- schedule PV installation inspections and maintenance according to a frequency defined with the installer, parallel to fire detection inspection provided by NBN S 21-100-2;
- train site technical staff to recognize warning signs (odor, discoloration, abnormal noise at the inverter level).
None of these measures derive from a single quantified regulatory obligation in Belgium to date: they follow from the general risk analysis principle that applies to every operator, with the prevention advisor at the forefront.